March to September 1996
Location: Lincoln and Memorial Apartments, Tulsa OK
Project: Retaining Walls Size: 7500 SqFt Approx
September 1996 to January 1997
Location: Woodland Manor 51 St and Memorial, Tulsa OK
Project: Retaining Walls Size: 12300 SqFt Approx
Builder: Flinco
January to May 1997
Location: Honey Creek Homes 81 St and Memorial, Tulsa OK
Project: Main entrance face, retaining walls & fence Size: 6500 SqFt
Builder: Michael Gordon
May to August 1997
Location: 71 St (Between) Harvard Ave & Lewis St, Tulsa OK
Project: Retaining walls Size: 7200 SqFt Approx
Builder: Sheerwood
August to November 1997
Location: Mrs Keth's Residence harvard and 76 St, Tulsa OK
Project: Retaining walls and various jobs
Builder: Owners
November 1997 to March 1998
Location: Marina Apartments, Tulsa OK
Project: Retaining walls in lake Size: 4500 SqFt Approx
Builder: Tulsa Tie Scaping
March to May 1998
Location: Family residence Harvard Ave & 93 St, Tulsa OK
Project: Retaining wall and rnovation of garden Size: 2000 SqFt Approx
May to June 1998
Location: Cancer Hospital Mingo St & 93 St, Tulsa OK
Project: Retaining wall Size: 4600 SqFt Approx
June to July 1998
Location: Senior Adult Assisted Living Facility, Barltesville OK
Project: Retaining walls Size: 2600 SqFt Approx
July to August 1998
Location: Apartments, Knoxville TN
Project: Retaining walls Size: 9400 SqFt Approx
August to October 1998
Location: Sand Spring Apartments, Sand Spring OK
Project: Retaining wall Size: 7300 SqFt Approx
October to December 1998
Location:Heart Medical Center Mingo St & 93 St, Tulsa OK
Project: Retaining wall Size: 2100 SqFt Approx
January to April 1999
Location: Various Small Jobs
Project: Lay rock, block, and concrete
Builder: Various
April to May 1999
Location: Zoo, Tulsa OK
Project: Steps on public stadium Size: 4500 SqFt Approx
Builder: City of Tulsa OK
May to July 1999
Location: Harvard & 58th St / 81 St & Sleepy Hollow
Project: Concrete reinforce walls Size: 4500 SqFt Approx
Builder: Owners
July to December 1999
Location: Trial joint the City of Tulsa OK with City of Sand Spring OK
Project: Retaining walls Size: 7800 SqFt Approx
Builder: City of Tulsa OK
December 1999 to April 2000
Location: Senior Houses 81 St & Yale Corner Southwest
Project: Retaining walls Size: 21000 SqFt Approx
Builder: Flinco
April 2000 to November 2001
Location:Various Jobs
Project: Lay rock, concrete block, brick & concrete
Builder: Various
November 2001 to January 2003
Location: I-40 Rest Area, Alandreed TX
Project: Lay concrete block, glass block & walls of rock Size: 26000 SqFt Approx
Builder: Marcus Construction
January to March 2003
Location: US 287 Rest Area, Hedley TX
Project: Mount native boulders Size: 5800 SqFt = 704 T Approx
Builder: Delco
March 2003 to December
During this time several jobs were preformed in the Amarillo area. Thoughout these months promotion for The Stone Masonry took place.